The Mid-Build Disaster That Nearly Left A New Build Development Empty – Here’s How We Fixed It

  • timgulley
  • Jul 24
  • 3 min read

Imagine this: you’re halfway through building Phase 2 of a major housing development. Homes are rising, roads are going in, buyers are lined up, and the developer’s reputation is on the line. But then – the foul water connection, agreed months earlier with the water company, is suddenly stopped.


This was the reality faced by our client earlier this year.


The problem nobody expected


Originally, the foul connection for Phase 2 was planned directly into the sewer network. Approvals were in place, work was underway. But mid-build, the water company raised unanticipated concerns that led to revoking the previously agreed route.


The consequences? Without a foul connection, NHBC sign-off was impossible. Without NHBC, no mortgages. No mortgages, no completions. The entire site risked becoming a dormant wasteland of half-built dreams.


An abandoned housing development

Our solution: Thinking beyond the original plan


With the developer and consulting engineer under immense pressure to avoid project paralysis, we were brought in to find an immediate yet robust solution.


The new plan required redirecting the foul drainage from Phase 2 via the adopted manholes of Phase 1. At first glance, simple. But Phase 1’s drainage was no ordinary gravity system. It included:


  • A complex valve system operated via radio signals to shut off the valve when the downstream sewer was full, preventing flooding for residents.

  • A site-wide warning system alerting residents and management via text when flood risk status was triggered.


The challenge: Integrating a pumping station without creating chaos


Our task was clear but daunting:


✅ Ensure Phase 2’s pumping station did not override, interfere with, or compromise the delicate Phase 1 valve and flood protection system.

✅ Ensure the pumping station automatically disabled when flood warnings were in place to avoid exacerbating any potential overflow.

✅ Deliver a solution acceptable to the water authority, NHBC, and the developer to allow site sign-off, mortgage approvals, and handovers to proceed.


The technical strategy


We worked closely with the consulting engineer, reviewing:

  • The radio signal protocols controlling the valve shut-off system.

  • The flood warning notification triggers and their communication architecture.

  • The operational sequence of Phase 1’s drainage under various load conditions.


We designed and installed an integrated control system linking the Phase 2 pumping station directly to the Phase 1 flood protection logic. This ensured:


🔧 Real-time synchronisation: The pumping station automatically disabled whenever a flood warning signal was active.


🔧 No backflow risk: Ensuring foul water from Phase 2 could never overwhelm the system in a flood event.


🔧 Clear alerts: All parties, including the site owner and residents, continued to receive instant text alerts whenever the flood warning was triggered.


The result: A development saved from standstill


Through rigorous coordination with the client and the consulting engineer, detailed control design, and robust commissioning processes, we delivered:


✅ Full compliance with the water authority requirements.

✅ NHBC sign-off on all homes.

✅ Homeowners able to complete mortgages and move in on time.

✅ A developer’s reputation protected – and a housing development brought to life rather than left dormant.


Final thoughts

This project demonstrated why foul water schemes are never just “pipes and pumps.” They are living systems that must integrate seamlessly with legacy infrastructure, emerging technologies, and environmental protection measures.


If your project demands technical excellence under pressure, get in touch. We turn blocked pathways into flowing successes – safeguarding your investments and delivering homes to those waiting to move in.

 
 
 

Comments


Address

Moduquip Ltd

35 Boulton Road

Reading

Berkshire

UK

RG2 0NH

Contact

Tel:   +44 (0) 330 390 4114

Email:  hello@moduquip.com

Opening Hours

Mon - Fri

7:30 am – 16:30 pm

© Copyright 2023 Moduquip Ltd.  All rights reserved.  Company Registered in England & Wales No. 11211524 | VAT Number 303263446

bottom of page